# New date proposed for notation rc.1 release
## Summary
- Total cost for code refactoring and rc.1 issues owned by MSFT
- implementation: `4 weeks` (starting from this week)
- PR review efficiency need to be secured
Proposal: Delay notation rc.1 release for 2 weeks, the new date is `Nov 28`
## Detail
Part I: Cost for pure refactoring
* cost for refactoring notation-go
* Implementation (`2 weeks` with UT, by Nov 15)
* PR review ()
* cost for notation CLI using new notation-go APIs
* implementation (`1 week`, no E2E test)
* Can only start after notation-go refactoring is done, so the earliest date is by Nov 22
Part II: The impact of refactoring
* Save costs for the following issues
* rc.1 issue [support `--debug` option](https://github.com/notaryproject/notation/issues/300)
* implementation (Cost reduced from 2 weeks to `0.4 week`)
* PR review ()
* rc.1 issue [Using Verifier without a repository](https://github.com/notaryproject/notation-go/issues/143)
* Cost reduced from 1 week to 0, covered by refactoring
* rc.1 issue [System vs User file/directory precedence](https://github.com/notaryproject/notation/issues/203)
* covered by refactoring
* Remove code for system directy but keep the extensibility for future implementation
* New issues fixed by refactoring
* Signing workflow is not fully compliant with spec
Part III: Other rc.1 issues owned by MSFT
* OCI artrifact support (high priority), covered by refactoring
* only E2E testing needed after refactoring
* [User Story] - Notation sign/verify Tag to Digest translation (high priority)
* cost: `0.6 week`
* E2E testing framework (medium priority)
* need improvement based on ORAS E2E solution
* * Notation list pagination (low priroity)
* Suggest to move to future