# Sync meeting on deliverables (2023-12-08)
present: Neja, Kenneth, Alan, ...
- notes of previous meeting below, should be added in MultiXscale OneDrive
- `> Project Management Material > Minutes > Deliverable Sync Meeting`
## Timeline goals
- complete draft ready by Fri 24 Nov (ready for review by others)
- feedback by Alan representing SC by Fri 1 Dec
- input for finalizing deliverables
- camera-ready by Thu 7 Dec, goes to SC
- final OK by SC by Tue 12 Dec
- ready to submit by Neja by Fri 15 Dec
- hard deadline 31 Dec for submitting
## Status overview of deliverables due M12
### D1.1 Report on shared software stack prototype [RUG, Bob/Pedro]
- status: 90% done
- being revised by Pedro/Bob after detailed feedback by Caspar
### D1.2 Plan for the design of a portable test suite [SURF, Caspar]
- status: 90% done
- Kenneth needs to put review comments, will version the document and implement the changes directly. Should be done by Monday
### D2.2 Exascale pathways for performance portable electrostatics solvers [FZJ,
Godehard]
- status: Outline is there
- Plan to write this weekend + Monday
### D5.1 Community contribution policy and GitHub App [UiB, Thomas]
- status: 95% done (6 pages)
- complete draft by Thomas
- detailed review & feedback by Kenneth
- revised by Thomas after feedback by Kenneth
- Thomas had an idea to mention CI/CD
- Matej's suggestion on CUDA
- **Zenodo link for releases?**
- review by Matej?
### D5.2 Support portal [UGent, Lara/Kenneth]
- status: ~75% done (16 pages, incl. 5 figures)
- still under review/revision by Kenneth (50% done)
- review done by Thomas, who thinks some important changes are still necessary
- handful of small tweaks still needed
- Should be ready by Wednesday morning, no issue expected
### D6.1 – Guidelines for Community Outreach, Education, and Training [UB, Alan]
- status: One section completed, other sections will probably be smaller
- Will work on it on the plane on 13/08
### D8.4 – Risk management Report [NIC, Neja]
- status: 85% done
- Matej read it
- Mitigation strategy for Castiel requests
- A few risks are still missing
- Requires input from Alan
- Will work on it today (12/08)
Next meeting Friday 8/12/23 1pm
------------------------------------------------------------------------------------------------------------------
# Sync meeting on deliverables (2023-11-29)
present: Neja, Kenneth, Alan, ...
- notes of previous meeting (2023-11-21) in MultiXscale OneDrive
- `> Project Management Material > Minutes > Deliverable Sync Meeting`
## Timeline goals
- ~~complete draft ready by Fri 24 Nov (ready for review by others)~~
- feedback by Alan representing SC by Fri 1 Dec
- input for finalizing deliverables
- ~~camera-ready by Thu 7 Dec, goes to SC~~
- final OK by SC by Tue 12 Dec
- ready to submit by Neja by Fri 15 Dec
- hard deadline 31 Dec for submitting
## Status overview of deliverables due M12
### D1.1 Report on shared software stack prototype [RUG, Bob/Pedro]
- status: Complete draft, except
- Some minor points which require reviewer input
- GPU input (from Alan?)
- Review: Caspar by 1.12.
### D1.2 Plan for the design of a portable test suite [SURF, Caspar]
- status: 75% done (15 pages, incl. lots of code snippets + 2-page appendix)
- complete draft by Caspar, reads "like a train"
- detailed review by Kenneth (though comments not added to Overleaf yet)
- high-level review by Lara
- is currently quite technical
- TODO
- revise based on feedback [Kenneth + Caspar]by the end of the week - 1/12/23
- final review by 3rd party (Alan and Matej) by 11/12/23
### D2.2 Exascale pathways for performance portable electrostatics solvers [FZJ,
Godehard]
- status: Hoping for a draft early next week
- first draft 4/12/23 - Neja email
### D5.1 Community contribution policy and GitHub App [UiB, Thomas]
- status: 95% done (6 pages)
- complete draft by Thomas
- detailed review & feedback by Kenneth
- revisted by Thomas
- handful of small suggestions made for minor tweak
- v0.2.0 release of GitHub App published: https://github.com/EESSI/eessi-bot-software-layer/releases
- **do we need a Zenodo link for releases?**
- contribution policy in place: https://eessi.io/docs/adding_software/contribution_policy
- also included in deliverable
- TODO
- review by Bob, Matej by 8/12/23
### D5.2 Support portal [UGent, Lara/Kenneth]
- status: ~75% done (16 pages, incl. 5 figures)
- rough draft by Lara
- under review/revision by Kenneth (50% done), in collaboration with Lara
- support portal itself is fully operational @ https://gitlab.com/eessi/support + https://eessi.io/docs/support
- weekly sync meetings in test rotation working (really) well
- support rotation for 2024 being planned
- see https://gitlab.com/eessi/support/-/wikis/Proposal-rotation-shedule
- TODO
- review by 3rd party (Thomas) by 8/12/23 ?
### D6.1 – Guidelines for Community Outreach, Education, and Training [UB, Alan]
- status: no change
### D8.4 – Risk management Report [NIC, Neja]
- status: CASTIEL2 gives us more work - another risk - mitigation -
- TO DO: Executive summary, finish the table
- Matej/Alan review by 8/12/23
Next meeting Friday 8/12/23 1pm