# ESG Optisolve - ESG GPT SPRINT PLAN ## Project Charter **Project Name:** ESG GPT MVP Development **Project Start Date:** February 1st, 2024 **Project End Date:** April 15th, 2024 **Project Team:** 1. ML Specialist 2. NLP Specialist 3. Backend Specialist 4. Frontend Specialist **Goal:** Develop a demoable MVP of the ESG GPT tool that showcases core functionalities. ## Sprint Plan ### Sprint 1: Feb 1 - Feb 14 **Objective:** Project setup and initial planning. - **All Team Members**: Project kick-off, understanding project requirements, and setting up development environments. - **ML and NLP Specialists**: Start exploring data sources and initial data collection. - **Backend Specialist**: Set up the initial backend framework. - **Frontend Specialist**: Draft basic UI design concepts. ### Sprint 2: Feb 15 - Feb 28 **Objective:** Data collection and initial backend setup. - **ML and NLP Specialists**: Continue data collection and start preprocessing tasks. - **Backend Specialist**: Develop basic API endpoints for data ingestion. - **Frontend Specialist**: Create wireframes for the user interface. ### Sprint 3: Mar 1 - Mar 14 **Objective:** Begin model development and API integration. - **ML Specialist**: Start building the base ML model. - **NLP Specialist**: Focus on initial NLP processing tasks. - **Backend Specialist**: Integrate APIs with ML/NLP tasks. - **Frontend Specialist**: Develop the basic front-end structure. ### Sprint 4: Mar 15 - Mar 28 **Objective:** Advanced model development and frontend-backend integration. - **ML and NLP Specialists**: Enhance ML/NLP models and start testing. - **Backend Specialist**: Ensure robust API functioning and backend-frontend integration. - **Frontend Specialist**: Start building interactive elements and connecting with backend. ### Sprint 5: Mar 29 - Apr 11 **Objective:** Refinement and testing. - **ML and NLP Specialists**: Finalize models and conduct thorough testing. - **Backend Specialist**: Strengthen API endpoints and ensure scalability. - **Frontend Specialist**: Refine UI/UX and conduct frontend testing. ### Sprint 6: Apr 12 - Apr 15 **Objective:** Final adjustments and preparation for the demo. - **All Team Members**: Bug fixes, final testing, and preparation for the demo. ## Milestones - **End of February**: Complete data collection and initial model development. - **End of March**: Achieve basic functionality with backend-frontend integration. - **April 15th**: MVP ready for demonstration. ## Final Deliverable - **MVP of the ESG GPT tool**: A basic version showcasing key features like ESG data processing and a simple user interface for interaction. ## Considerations - Weekly team meetings for progress tracking and agile adjustments. - Flexibility in the plan to accommodate learning curves and unforeseen challenges. - Focus on collaboration between team members to ensure integration of different components. This plan is designed to effectively utilize the skills of each team member and progressively build towards a functional MVP within the given timeframe. Regular evaluations at the end of each sprint will ensure the project remains on track and any issues are addressed promptly.