## January 12
* Roman
* Small company, people are not aware that is happening in the other parts of the org
* There have been cases when information has been missed
* Do not know what to do when blocked
* Not enough releases
* Standups are not fulfilling their purpose
* Richard
* There was friction with putting together a feature
* There was misalignment behind the feature
* No understanding of the design
* Designs were not properly captured
* A lot of back and forth because the requirements and design we not clear
* Meetings are at the right time
* Ben
* CI infrastructure in not mature
* Meetings are at the right time
* Harald
* Meeting time is good because it is in the afternoon
Go over the issues
Have a clear agenda
Issue tracker was used a way to create an agenda
## Decision Summary
* We will start to triage again
* We will use the project board
* We will add the column for priorities - Epics
* We will run sprints 2 weeks
* We will have a release every 2 weeks
* We work on features the first week and bugfix the second.
* We will have feature freeze -
* Create release branches - for every bump of minor or major (not patch) version
* We will decompose the epics - have a planning meeting for a sprint
* Every first standup of a sprint we do planning
* Monday Demo
* Tuesday release party
* Wednesday planning next sprint
* Thursday design meeting of the release week is retro
* We will update the board columns to make it more useful to meet the flow
* If you do not like the reviewers change them
* Add a column for the reviews