title: 'Brixton Mint CCF Bid timeline'
---
Brixton Mint CCF Bid Phase1
===
Project Timeline
---
```mermaid
gantt
title Brixton Mint Phase 1 - Sep '22 - Jan '23
dateFormat YY-MM-DD
axisFormat %W-'%y
Project start : milestone, mile1, 22-09-01,0.1d
section Engagement
Engagement Strategy : strategy, after mile1,5d
Publicity: after strategy, 80d
Community for Event 1 : comme1, after strategy, 27d
Community for Event 2 :comme2, after comme1 , 25d
Community for event 3 : comme3 , after comme2,25d
section Planning
Engage Project Co-ordinator : 22-09-01,5d
Confirm Venues : v1, 22-09-01, 10d
Event partners: 22-09-01 , 10d
section Event 1
Gear up: ge1, after comme1 , 3d
Final Prep :prep1, after ge1, 1d
EVENT 1 : milestone, event1,after prep1,1d
Consolidation : ec1,after event1, 7d
Debrief : after ec1,1d
section Event 2
Gear up: ge2, after comme2 , 3d
Final Prep :prep2, after ge2 , 1d
EVENT 2 : milestone, event2,after prep2,1d
Consolidation :ec2, after event2, 7d
Debrief : after ec2,1d
section Event 3
Gear up: ge3, after comme3 , 3d
Final Prep :prep3, after ge3 , 1d
EVENT 3 : milestone, event3,after prep3,1d
Consolidation : ec3, after event3, 7d
Debrief :deb3, after ec3,1d
section Monitoring
Info gathering: infog, after deb3, 30d
section reporting
Reporting: reort, after infog, 10d
```