The following table identifies Classes of Development that are classified as Accepted Development subject to meeting the Accepted Development Classification Criteria
<table style="width:100%">
<tr>
<th>Class of Development</th>
<th colspan="2">Accepted Development Classification Criteria</th>
</tr>
<tr>
<td>Air handling unit, air conditioning system or exhaust fan
Except where any of the following apply:
Local Heritage Place Overlay
State Heritage Area Overlay
State Heritage Place Overlay</td>
<td>The item will be installed on or within an existing building
The item being installed does not encroach on a public street or affect the ability of the building to resist the spread of fire.
If the associated building is in a Historic Area Overlay, no part of the item, when installed, will be able to be seen by a person standing at ground level in a public street</td>
</tr>
<tr>
<td>Brush fence
Except where any of the following apply:
Hazards (Flooding) Overlay
Historic Area Overlay
Local Heritage Place Overlay
Ramsar Wetlands Overlay
State Heritage Area Overlay
State Heritage Place Overlay</td>
<td>The fence is formed (wholly or partially) from brush
The fence does not exceed 2.1m in height (measured from the lower of the 2 adjoining finished ground levels)
The fence does not exceed 1m in height within 6m of the intersection of 2 boundaries of land where those boundaries both face a road, other than where a 4 x 4 m corner cut-off has already been provided (and is to be preserved)
The development will not be located within the extents of the River Murray 1956 Flood Level as delineated by the SA Property and Planning Atlas.</td>
</tr>
<td>Building work on railway land
Except where any of the following apply:
Coastal Areas Overlay
Hazards (Acid Sulfate Soils) Overlay
Local Heritage Place Overlay
Significant Landscape Protection Overlay
State Heritage Area Overlay
State Heritage Place Overlay</td>
<td>Building work is associated with a railway
It is situated (or to be situated) on railway land (within the meaning of Schedule 4 clause 14 of the Planning, Development and Infrastructure (General) Regulations 2017)
It is required for the conduct or maintenance of railway activities
It does not involve the clearance of native vegetation
The development will not be located within the extents of the River Murray 1956 Flood Level as delineated by the SA Property and Planning Atlas. </td>
</tr>
</tr>
<td>Internal building work
Except where any of the following apply:
Local Heritage Place Overlay
State Heritage Area Overlay
State Heritage Place Overlay</td>
<td>There will be no increase in the total floor area of the building
Other than where located within the Historic Area Overlay there will be no alteration to the external appearance of the building to any significant degree.
There will be no alteration to the external appearance of the building where located within the Historic Area overlay. </td>
</tr>
</tr>
<td>Partial demolition of a building or structure
Except where any of the following apply:
Historic Area Overlay
Local Heritage Place Overlay
State Heritage Area Overlay
State Heritage Place Overlay</td>
<td>None.</td>
</tr>
</tr>
</tr>
<td>Shade sail
Except where any of the following apply:
Coastal Areas Overlay
Future Road Widening Overlay
Historic Area Overlay
Local Heritage Place Overlay
Ramsar Wetlands Overlay
Significant Landscape Protection Overlay
State Heritage Area Overlay
State Heritage Place Overlay</td>
<td>The development will not be contrary to the regulations prescribed for the purposes of section 86 of the Electricity Act 1996
The development will not be built, or encroach, on an area that is, or will be, required for a sewerage system or waste control system
Shade sail consists of permeable material
The total area of the sail - does not exceed 40m2
No part of the shade sail will be:
3m above ground or floor level (depending on where it is situated) at any place within 900mm of a boundary of the allotment
5m above ground or floor level (depending on where it is situated) within any other part of the allotment
Primary street setback - at least as far back as the building line of the building to which it is ancillary
If any part of the sail will be situated on a boundary of the allotment, the length of sail along a boundary does not exceed 11m
In a case where any part of the sail or a supporting structure will be situated on a side boundary of the allotment - the length of the sail and any such supporting structure together with all relevant walls or structures located along the boundary will not exceed 45% of the length of the boundary.
Does not involve the clearance of native vegetation.
The development will not be located within the extents of the River Murray 1956 Flood Level as delineated by the SA Property and Planning Atlas</td>
</tr>
</tr>
</tr>
<td>Partial demolition of a building or structure
Except where any of the following apply:
Historic Area Overlay
Local Heritage Place Overlay
State Heritage Area Overlay
State Heritage Place Overlay</td>
<td>The development will not be contrary to the regulations prescribed for the purposes of section 86 of the Electricity Act 1996
The system is freestanding and not attached to a building or other structure.
No part of the system:
is more than 4m in height (measured as a height above the natural surface of the ground);
is within 100m of a dwelling not associated with the system (whether the dwelling is on the same allotment as the system or another allotment);
and
is within 10m of a boundary of an allotment containing a dwelling not associated with the system.
The generating capacity of the system does not exceed 30 kW
Does not result in the clearance of any native vegetation.</td>
</tr>
</tr>
</tr>
</tr>
<td>Partial demolition of a building or structure
Except where any of the following apply:
Historic Area Overlay
Local Heritage Place Overlay
State Heritage Area Overlay
State Heritage Place Overlay</td>
<td>The development will not be contrary to the regulations prescribed for the purposes of section 86 of the Electricity Act 1996
The system is freestanding and not attached to a building or other structure.
No part of the system:
is more than 4m in height (measured as a height above the natural surface of the ground);
is within 100m of a dwelling not associated with the system (whether the dwelling is on the same allotment as the system or another allotment);
and
is within 10m of a boundary of an allotment containing a dwelling not associated with the system.
The generating capacity of the system does not exceed 30 kW
Does not result in the clearance of any native vegetation.</td>
</tr>
</tr>
</tr>
</tr>
</tr>
<td>Swimming pool or spa pool
Except where any of the following apply:
Coastal Areas Overlay
Future Road Widening Overlay
Hazards (Acid Sulfate Soils) Overlay
Hazards (Flooding) Overlay
Historic Area Overlay
Local Heritage Place Overlay
Significant Landscape Protection Overlay
State Heritage Area Overlay
State Heritage Place Overlay
Water Resources Overlay</td>
<td>The development will not be contrary to the regulations prescribed for the purposes of section 86 of the Electricity Act 1996.
The development will not be built, or encroach, on an area that is, or will be, required for a sewerage system or waste control system.
It is ancillary to a dwelling erected on the site or a dwelling to be erected on the site in accordance with a development authorisation which has been granted.
Allotment boundary setback - not less than 1m.
Primary street setback - at least as far back as the building line of the building to which it is ancillary.
Location of filtration system from a dwelling on an adjoining allotment:
not less than 5m where the filtration system is located inside a solid structure that will have material impact on the transmission of noise; or
not less than 12m in any other case.
Does not involve the clearance of native vegetation.
The development will not be located within the extents of the River Murray 1956 Flood Level as delineated by the SA Property and Planning Atlas.</td>
</tr>
</tr>
</tr>
</tr>
</tr>
<td>Water tank (underground)
Except where any of the following apply:
Coastal Areas Overlay
Hazards (Acid Sulfate Soils) Overlay
Ramsar Wetlands Overlay</td>
<td>The development will not be built, or encroach, on an area that is, or will be, required for a sewerage system or waste control system
The tank (including any associated pump) is located wholly below the level of the ground.
Does not involve the clearance of native vegetation.</td>
</tr>
</tr>
</tr>
</table>