Plan of KaaS onboarding
=======================
```mermaid
gantt
axisFormat %m-%d
excludes weekends,2022-04-04,2022-05-02,2022-05-03,2022-05-04,2022-06-03,2022-09-10,2022-10-03,2022-10-04,2022-10-05
section Data Catalog
Usage Analysis: active, analysis, 2022-03-01, 15d
Email for onboarding:done, 2022-02-25, 1d
Catalog onboarding meeting: active,meeting, 2022-03-07, 3d
Finish onboarding: f_DC, after meeting, 3d
section MetaManagement
Get Access to MetaManager: acMM, after f_DC, 5d
Provide MetaManager JIRA access: done,2022-03-04, 1d
section Configuration
Update Data Dic: after f_DC, 5d
Configure topic: after acMM, 5d
section Devleopment
Coding: develop, after analysis, 1w
Test:test, after develop, 1w
section Promote to UAT
UAT : uat, after test, 2w
section Promote to Prod
Release: Future, after uat, 1w
```