# MultiXscale sync meeting 2022-10-24
## Notes
- **PO is on leave, back on 2 Nov 2022, we should reply by then**
- includes new Gantt chart, etc.
- partners should complete there work no later than Mon 31 Oct
- edit shared doc with track changes enabled
- points raised by Barbara
- PO accept to indicate whether each participant is EuroHPC member
- unclear why this was requested
- Carlo: this question was raised for all CoE's
- mostly relevant for industry partners
- goal is to understand if partners are already contributing to EuroHPC
- unclear whether this is about individuals or institutions or countries
- someone should check which partners are missing from EuroHPC
- PM distribution are linked to task distribution
- no plans to change effort per partner, only tweak planning of tasks within WPs
- points 6/7/8: each partner should reply via email on this
- Matej: question by laywer on how steering committee (SC) is composed
- proposal is to just use WP leaders => OK?
- no objections
- Carlo: maybe a subset of WP leaders to avoid making SC too large?
- SC members:
- scientific part: who?
- service part: who?
- Matej as coordinator
- Alan
- Sara
## Revising WP tasks
- WP1 (development of EESSI service) + WP5 (support/maintance of EESSI service)
- 1 additional "consolidation" task T_X
- some effort for tasks T_X-T_(X-1) is moved into T_X
- start/end month of current tasks T-X-T_(X-1)) is adjusted (shortened)
- WP1
- T1.1 (stable service): M1-M24
- T1.2 (extending support): M9-M30
- T1.3 (test suite development): M1-M24
- T1.4 (RISC-V): M12-M48
- T1.5 [new] (consolidation): M24-M48
- WP5
- T5.1 (support "portal"): M1-M12
- T5.2 (testing): M6-M30
- T5.3 (bot): M-1-M12
- T5.4 [new] (consolidation): M12-M48
- total effort remains the same for WP1 + WP5
- deliverables fpr WP1 + WP5 are revised accordingly
- for WP1: from 4 to 7 deliverables
- intermediate + final report for T1.1 + T1.3 (2xM12, 2xM24)
- 1 final report for T1.2, T1.4, T1.5 (1xM24, 2xM48)
- for WP5: from 4 to 5 deliverables
- final report for T5.1 + T5.3 (M12)
- final report for T5.2 (M30)
- intermediate + final report for T5.4 (M30, M48)
- reporting efforts spread across partners involved in WP1 + WP5
- need to check where UB (Alan) would be involved in reporting effort
- also need to check deliverables for RUG
- Caspar (SURF) and Kenneth (UGent) are making necessary changes in shared doc for WP1 + WP5
- WP2
- first deliverable would be split between WP2 partners, individual report from each partner involved
- more details needed on what will be done with waLBerla
- Sauro: may not be waLBerla in the end, is that a problem formally if it's not?
- flexibility of maybe switching to another software should be clear in task description
- other option is OpenLB
- both are frameworks which can be extended, need to check which one is better
- Alan: problem with ?? should be fixed, Sauro agrees
- Rudolf has changed their deliverable, focused on ESPRESSO, due M9
- WP3
- one more deliverable needed here?
- currently 2 deliverables, should be 3 (one more for T3.5)?
- WP4
- already has 4 deliverables, should be one more at minumum
- WP6
- Alan will do similar effort, shift things around
- D6.1 will shift to M12 to cover first reporting period
- current 4 deliverables will stay as is
- WP7
- HPCNow is missing deliverables in 3 reporting periods
- D7.2 in M24 (by NIC)
- D7.4 in M40 (by HPCNow!)
- can the partner for these be swapped?
- that would mean two deliverables for NIC in M40 => stagger one to M45?
- Alan/Matej: yes, ok to swap
- one extra deliverable
- Leonardo and IIT need to provide 2 more deliverables
- one extra already covered by splitting 1st deliverable in WP2
- should also be in different reporting periods
- PO asked for this so there is reporting for all effort being done
- Sauro (IIT) and Carlo (Leonardo) will discuss this
- issue with budget for JSC due to double counting of overhead
- feedback of project officer needed for this to see what is possible w.r.t. reallocating that PM budget
- Barbara can share contact info for "in-case-of-emergency" person for this with Godehard
- Alan: concerns ~122K euro (~12PMs)
- options:
- reuse money
- to fix problem with underestimate of Leonardo's effort?
- Carlo: can't shift money from one country to another at this point
- Volker: may not be a problem?
- Italy's budget contribution was approved already, increasing that is problematic
- Godehard: would imply that (some) of the money can only be reallocated to Univ. of Stuttgart
- Alan: could be motivated due to request for additional deliverables
- give money back, because doing something else is too complicated
- next sync call: Fri 28 Oct at 11:00 CEST
- Sauro is travelling
- OK for the others
- Sauro is requesting to make sure that his GMail is always in CC in important communication on the project